Oracle Primavera P6
Manage projects of any size with Oracle Primavera P6 in either on-premise or cloud-based, robust, and easy-to-use solution for globally prioritizing, planning, managing, and executing projects, programs, and portfolios
Oracle Primavera P6
Global
No data available.
No
Managing Risk in Primavera Risk Analysis Training (3 Days)
What you will learn:
This course provides training for Primavera’ s Risk Management solution. Participants will gain a thorough background in the basic concepts of risk management. This three-day class leads you through examples of specific risk modeling techniques and provides a lab-style workshop on the third day to allow students to apply the learned techniques.
Learn to:
Suggested Prerequisites:
Audience
Course Objectives:
Course Topics:
-----------------------------------------------In Turkish-----------------------------------------------------------------------------------------------
Primavera Risk Analizi ile Proje Risklerini Yönetme (3 Gün)
Neler Öğreneceksiniz?
Primavera yazılım ailesindeki Proje Risk Analizi ürünü ile projelerde risk yönetimi ve analizi yapılması öğretilir. Katılımcılar, risk yönetimin temel kavramını öğrenirler. Eğitimde 3 gün boyunca örnek uygulamalar eşliğinde özel risk modelleme teknikleri üzerinde durulur ve proje risk senaryoları üzerinden alıştırmalar yapılır.
Özet:
Ön Koşullar:
Katılımcılar
Kursun Hedefleri:
Kurs Başlıkları:
Advanced Project Management in Primavera P6 Training (2 Days)
What you will learn:
This course provides in-depth project management training in P6. Topics include updating baselines, importing and exporting project data, and top-down budgeting.
Detailed instruction on earned value analysis includes lessons on duration types and how to calculate percent complete. Students also will learn to leverage best practices to create a project using methodologies.
Learn to:
Audience
Suggested Prerequisites:
Course Objectives:
Course Topics:
Assigning Codes
Using User-Defined Fields and Global Change
Advanced Scheduling
Importing and Exporting Data
Updating Baselines
Claim Digger
Calculating Percent Complete
Earned Value Analysis
Activity Usage Profile and Spreadsheet
Auto Compute Actuals
Analyzing Resources and Roles
Manually Allocating Resources
Using Bucket Planning
------------------------------------------------In Turkish-------------------------------------------------------------------------------------
Oracle Primavera P6 ile Proje Yönetimi İleri Eğitimi (2 Gün)
Genel Bilgiler:
Bu kurs Primavera P6 ile Proje Yönetimi için kapsamlı bir eğitim sunar. Proje kazanılmış değer analizi, ilerleme yüzdeleri, import ve export ile veri transferi gibi birçok önemli konu bu eğitimi başlıkları içinde yer alır.
Katılımcılara eğitim sonunda onaylı ve imzalı olarak ileri düzeyde Oracle Primavera P6 sertifikası verilir.
Neler Öğreneceksiniz:
Önbilgi Gereksinimi:
Katılımcılar:
Eğitimin Hedefleri:
Kurs Başlıkları:
Kod Atama
Kullanıcı Tanımlı Alanlar ve Toplu Değişiklik
İleri Çizelgeleme (Scheduling)
Veri Import ve Export
Hedeflan (Baseline) Güncelleme
Yüzdesel İlerleme Hesaplamaları
Kazanılmış Değer Analizi
Aktivite Kullanım Profili ve Tablosu
Detaylı Kaynak Analizi
Kaynak tarihlerinin elle ayarlanması
Kaynak dağılımını elle belirleme
Claim Management and Delay Analysis Training (2 Days)
What you will learn:
This course provides training for Claim Management theory with case study examples on project management software. Participants will gain knowledge through the basic concepts of claim management and delay analysis. This two-day class leads you through examples of specific claim analyzing tools, techniques and provides a lab-style workshop, and allow students to apply the learned techniques in scenario projects.
Learn to:
Suggested Prerequisites:
Audience
Course Objectives:
Course Topics:
Project Management in Oracle Primavera P6 Training (3 Days)
What you will learn:
This course provides hands-on training for Primavera’s client/server-based solution, leading participants through the entire project life cycle, from planning to execution. Topics include adding activities, assigning resources, and creating a baseline. Participants also gain a thorough background in the concepts of planning and scheduling.
All workshops and instruction stress the three basic elements of project management: schedule, resource, and costs.
Learn to:
Suggested Prerequisites:
Audience
Course Objectives:
Course Topics:
Data, Navigating, and Layouts
Enterprise Project Structure
Creating a Project
Creating a Work Breakdown Structure
Adding Activities
Creating Relationships
Scheduling
Assigning Constraints
Maintaining the Project Documents Library
Formatting Schedule Data
Roles and Resources
Assigning Resources and Costs
Analyzing Resources
Optimizing the Project Plan
Baselining the Project Plan
Project Execution and Control
Reporting Performance
Project Web Site
--------------------------------------------------------------------------------- In Turkish-------------------------------------------------------------------
Oracle Primavera P6 ile Proje Yönetimi Temel (3 Gün)
Genel Bilgiler:
Bilgisayar başında uygulamalı olarak devam eden bu üç günlük Primavera P6 Temel eğitiminde, bütün proje yönetimi yaşam döngüsü planlamadan yürütmeye kadar öğretilir. Katılımcılara eğitim sonunda onaylı ve imzalı olarak temel düzeyde Oracle Primavera P6 sertifikası verilir.
Proje yönetimin üç temel elementi olan zaman, kaynak ve maliyet başlıkları üzerinde ağırlıklı olarak durulur. Primavera P6 yazılımı ile birlikte ayrıca temel düzeyde proje yönetimin mantığı da anlatılır.
Neler Öğreneceksiniz:
Önbilgi Gereksinimi:
Katılımcılar:
Eğitimin Hedefleri:
Kurs Başlıkları:
Veri tipleri, Navigasyon ve Layoutlar
Kurumsal Proje Yapısı
Proje Oluşturma
WBS Oluşturma
Aktiviteleri Ekleme
İlişkileri Oluşturma
Çizelgeleme (Scheduling) - CPM
Kısıtlamaları Atama
Aktivite Kodları
Proje Verilerini Düzenleme
Kaynak Ve Roller
Kaynak ve Maliyet Atama
Kaynak Analizi
Proje Planını İdealize Etme
Hedef Plan Oluşturma (Baseline)
Proje Yürütme ve Kontrol
Performans Raporlaması
Oracle Primavera Project Schedule Quality Check Metrics (AKIM Engineering)
Constraints
Schedule constraints have a significant effect on risk analysis results. They should be used sparingly, and only when the constraint reflects reality. Constraints to be particularly aware of are: • Must start on and Must finish on – preceding delays will not delay the task, and preceding time savings will not bring it earlier • Start on or after (SNET) and Finish on or after (FNET) – preceding time savings will not bring the task earlier Consider removing these constraints and replacing them with logic (e.g. Finish-to-Start links) instead. Other types of constraints are less significant because they do not influence the tasks' dates, only their floats. For example, you can use a Finish on or before constraint to indicate the desired completion date of a task – this will not force the task to finish on that day, but the shortfall will be indicated in the task's float.
Open-ended tasks (Does not include ignored links)
For a schedule risk analysis to be meaningful, it is important that tasks' dates are set by logic (e.g. Finish-to-Start links) rather than constraints. This is so that the risk analysis will recognize the knock-on effect of delays. An open-ended task is one that does not have at least one predecessor and one successor – it indicates a possible lack of logic. Consider closing open-ended tasks: • If a task has no predecessor, try to find some other tasks which could potentially delay it. Leave it as open-ended if it is the project start milestone. • If a task has no successors, try to find some other tasks which it could potentially delay. Leave it as open-ended if it is a project finish or reporting milestone.
Out of sequence updates ("broken logic")
The logic in a plan can be broken when tasks have started or finished before their predecessors. It is Constraints
It is recommended that any broken logic is removed or corrected to ensure the project schedules as expected. For example, if task A has a Finish-to-Start link to task B, but B has been started (by giving it an Actual Start date), this is broken logic. It is not clear whether B's remaining work should wait for task A to finish, or start straight away. Consider fixing the broken logic by either removing the link or removing the actual dates. Also, consider using the retained logic/progress override options on the Scheduling tab of the Plan | Options dialog box.
Lags longer than 0 Day
A lag is a gap in the logic between two tasks – a delay between the dates of two tasks that are linked together. Lags cannot have risk or uncertainty. In reality it is likely that the lag represents either work or a delay, whose duration is uncertain. This is particularly significant for long lags. Consider replacing the lag with a task, so that uncertainty and risks can be assessed against it. Use the Convert Lags to Tasks tool when a project contains a large number of long lags.
Negative lags ("leads")
A negative lag is an overlap in the logic between two tasks – often it is used to represent a task starting earlier, with sufficient time allow some other work to happen. Lags cannot have risk or uncertainty. In reality, it is likely that the negative lag represents a necessary overlap, whose duration is uncertain. Consider replacing a negative lag with another kind of link that does not need the lag. For example: • Replace a negative lag on a Finish-to-Start link with a positive lag on a Start-to-Start link. • Split the tasks so that the overlap is explicitly represented by a task.
Positive lags on Finish-to-Start links
A lag is a gap in the logic between two tasks – a delay after one task finishes before the next one starts. Lags cannot have risk or uncertainty. In reality, it is likely that the lag represents either work or a delay, whose duration is uncertain. Consider replacing the lag with a task, so that uncertainty and risks can be assessed against it. Use the Convert Lags to Tasks tool when a project contains a large number of long lags.
Start-to-Finish links
Start-to-Finish links are used deliberately very rarely because they have the unusual effect that the successor happens before the predecessor. Consider whether this logic might be a mistake, especially if it is between tasks that are not milestones.
Lags between tasks with different calendars
A lag is a gap in the logic between two tasks – a delay between the dates of two tasks that are linked together. When the two tasks have different calendars, it is not clear which calendar the task will use – whether it is the preceding task's or the succeeding task's calendar. Consider replacing the lag with a task, so that its calendar can be explicitly defined. Use the Convert Lags to Tasks tool when a project contains a large number of long lags.
Links to/from summary tasks
Many people prefer not to put predecessors or successors against summary tasks, because other project management tools (such as Primavera P6) do not support them. Consider removing logic on a summary task, by using a milestone to represent the start or finish of all the tasks in the summary heading, and putting the link on the milestone instead of the summary task.
AKIM ENGINEERING Consulting Company; as Primavera Specialized Oracle Gold Partner, established in 1994 and providing Primavera consulting and implementation & integration services as well as delivering internationally recognized Primavera certified training. AKIM Engineering is also providing Primavera software installation and technical/how-to support, help desk service, and problem-solving regarding project management and planning with Oracle Primavera software. We do also provide official oracle primavera software licenses, as an Engineering and Construction Industry specialized company and work as Authorized Representative for Primavera products.
We are also experts in building Primavera baseline schedules as well as executing, updating, and reporting project schedules. We help customers to build PMO and learn/implement performing earned value management, resource capacity planning, and resource leveling, project risk management, Monte Carlo risk simulation, delay analysis, and claim management, ERP integration with Primavera services in Oracle Primavera at their project environment. We also have experience in successfully integrating Oracle Primavera products into client organizations, significantly improving their project management and planning capabilities. Our internationally certified training classes address user adoption challenges by combining both tool use and project management & planning theory.is a team of dedicated professionals that specialize in various engineering disciplines and provide project management consulting services to our clients in different industries since 1994. We are official Primavera Authorized Representative and we do provide Primavera trainings, technical support, consulting services and Primavera license sales.